Parish Life Building Construction

What are the latest news?

Live Cam 1

Live Cam 2

Posted: November 8, 2019

  • The concrete floor for the Fellowship Hall was poured on Tuesday, November 5.
  • Work continues on installing storm drain piping. Started at the detention pond and are now past the Conner Ministry Building and along the south side of the Parish Life Building.
  • Work continues in clearing the athletic field on the far side of the Brown Rd house.
  • Monday the block walls around the Fellowship Hall will begin to be installed

Posted: October 31, 2019

  • No construction the next few days due to rainy weather.  The good news is that sunshine is in the forecast starting Friday.
  • The blocks that go on the concrete footings are mostly installed.  Gravel has been put in under where the Fellowship Hall floor will be.
  • Pouring of the Fellowship Hall concrete floor is expected to take place early Tuesday morning.
  • Installation of the storm drain system has been taking place by the CMB.

Posted: October 25, 2019

  • This week the blocks that go on top of the foundation are being installed. The concrete slab for the Fellowship Hall (center section) will be poured within the next two weeks, weather permitting.
  • Grading of the expanded detention pond area is essentially done.
  • Clearing for the Athletic Field on the far side of the Brown Road house is well underway.

Posted: October 18, 2019

  • This week the trenches for the building foundations were dug, rebar installed, and concrete poured for the footings.  Concrete trucks were onsite between 4:30 a.m. and 7 a.m. on the morning of Friday, October 18 to complete the concrete pour.
  • Grading of the expanded detention pond area will be completed within the next two weeks.
  • Clearing for the Athletic Field on the far side of the Brown Road house has begun.

Posted: October 11, 2019

Keep checking this page for the latest updates!

Posted: October 8, 2019

A Peek Behind the Fence

Click on the image to see construction photos
From day 1 to present

 

Posted: October 2, 2019

What you should know regarding parking and playground ...

Weekend Masses:

Playground:
Weekdays: The Playground will be closed while construction takes place in the vicinity of the playground.
The playground will be open in the afternoons and on weekends ONLY IF the fenced area is open to give access to the playground.


Overall Zone of Construction Activities
These are the areas that will be impacted at some point during the construction period.  The areas directly around the new building will be impacted for the entire construction period.

 

 

Give a timeless remembrance!

Have questions?


If your question is concerning something ...

Inside the Fence, contact Deacon Roger

Outside the Fence, contact Michael McGarry

For questions regarding the Capital Campaign, contact Bob Cardone

Online Giving

Online Giving

Secure and Convenient Donate now!